Asbestos sheeting
Asbestos sheeting must be bundled securely, and the bundles must be double wrapped in 200 micron plastic sheeting, with each bundle of sheeting sealed with adhesive tape along every lap prior to placement into the skip.
The wrapped material may be transported in a roll on roll off skip. The skip must be lined with one layer of 200 micron plastic before loading to assist the packaged asbestos to safely slide to the designated area at the disposal point.
If a roll off bin is not used, the asbestos must be double wrapped and taped as before. If unloaded manually or by mechanical means, e.g. crane, truck, etc., it must be placed into the excavation in a manner that does not allow damage or puncturing of the plastic.
Watch the video below:
Transport and Disposal of Asbestos Waste
Asbestos waste transported to a disposal site must be packaged in the following manner:
Unloading the Tip Site
The transporter should carefully reverse into position at the designated disposal point, lower the skip and carefully tilt the skip to allow the asbestos to fall into the excavation, care should be taken to ensure that no damage or puncturing of the plastic occurs. The driver should ensure that all necessary documentation is in order before leaving the disposal site. All contamination waste is to be transported in EPA licensed vehicles only.
Watch the video below: